Massive navy packages face a coordination drawback when taking over broad and interdependent program targets. Whereas small packages with decoupled groups can usually depend on a extra ad-hoc method to planning and roadmaps, massive packages with advanced dependencies usually should develop grasp schedules that may embody as many as 50,000 components. In such an setting, groups want to have the ability to coordinate efforts and meet cross-cutting targets. Within the absence of higher instruments, when tasked with a serious program goal, groups flip to PowerPoint to stipulate quarterly actions. Whereas such an method affords some visibility into program actions, the tip result’s a slide deck that will solely be present for 4 days per 12 months, since there isn’t any direct mechanism for updating the doc between quarterly updates. Along with creating overload, this method is insufficient to reply three crucial questions:
- Is there something you deliberate to finish final quarter however didn’t? If that’s the case, what’s the affect?
- How assured are you about finishing commitments this quarter?
- Is there anybody you’re depending on, and are they conscious?
In aviation, waypoints information pilots by advanced flight plans, offering construction whereas sustaining flexibility. Impressed by this aviation precept, I labored with Lieutenant Colonel Adam Satterfield of america Air Pressure to create a light-weight digital framework that may assist main packages plan, observe, and execute main targets. This put up explains how the Waypoints Framework can present program managers with a light-weight digital method to visualizing main actions, synchronizing dependencies throughout groups, and managing dangers.
The Origin of Waypoints
As a Program Administration Officer in america Air Pressure, Lieutenant Colonel Satterfield oversees main protection packages. Lt. Col. Satterfield, a co-creator of Waypoints, had a sheet of paper hanging up in his cubicle that outlines the concepts that turned the origin of Waypoints. Lt. Col. Satterfield had beforehand met with the Colonel accountable for his main program, who listed three necessities for Waypoints:
- It must be easy.
- It must be led by the workforce leaders.
- It wants to visualise the work.
To realize these necessities, Lt. Col. Satterfield understood {that a} minimal viable framework was wanted to bridge the hole between casual planning and complete mission administration. The framework wanted to have the ability to deal with coordination wants with out overwhelming the group.
Lt. Col. Satterfield started collaborating with us, and our preliminary step was to consolidate our planning efforts in Excel. Whereas this shift improved dependency visibility and created a single supply of knowledge, quarterly accuracy issues endured.
The breakthrough got here once we migrated to Jira and Confluence. Jira allowed us to trace particular person waypoints as points, whereas Confluence supplied information administration and dynamic dashboards. It allowed groups to filter waypoints into quarterly buckets, kind by due date, and hint paths towards objectives, decreasing cognitive overload whereas enabling steady updates.
Extra importantly, this digital method basically modified the group’s planning mindset. As an alternative of ready for quarterly opinions to find {that a} milestone had been missed, program managers now had perception into points and progress in close to actual time. Groups might alter course instantly as soon as a difficulty arose somewhat than discovering issues months after they emerged.
Far too usually, program managers mistakenly ask, Are we the place we wish to be? As an alternative, they need to be asking, Are we on the appropriate trajectory?
The mindset related to the primary query concerned lacking a mark earlier than correcting course. The latter permits for corrections en route, much like a pilot adjusting the heading of an airplane between waypoints somewhat than discovering that they missed their vacation spot as a result of the winds pushed them off target.
Constructing the Waypoints Framework
The Waypoints Framework makes use of a light-weight digital method to visualise main actions, synchronize dependencies, and handle dangers. Jira and Confluence are the 2 main digital instruments that allow the framework. The Waypoints journey usually begins with a aim {that a} program desires to realize in two or three years that’s usually made public due to its significance to the complete group, equivalent to the primary flight of the B-21 stealth bomber in November 2023. Attaining that main aim requires the trouble of a number of groups.
Every workforce in this system enterprise establishes its personal waypoints main towards this main programmatic aim, which creates a visual path that everybody in a company can observe. Every waypoint represents a promise, a deliberate exercise that unlocks one other programmatic exercise towards a aim.
The Waypoints Framework rests on three rules:
- Proper-sizing: To assist distill complexity to a understandable degree, the group’s workforce leaders will establish two-to-eight actions per quarter per workforce with these groups sustaining detailed planning utilizing no matter instruments work greatest. When too many actions are deliberate, the trouble to keep up correct plans will increase. Maintaining the quarterly deliberate accomplishments to single digits helped make sure the plan’s accuracy. For every exercise, every workforce will establish their definition of carried out and description main contributions in direction of the foremost programmatic aim set forth. This step alone can usually be an early indicator of mismatches and incorrect handoffs.

Determine 1: The primary precept, right-sizing, limits the variety of actions per quarter to enhance plan accuracy.
- Time-phasing: The Waypoints Framework requires high-fidelity planning for the present quarter plus the following two, medium-fidelity for the next two six-month durations, and lower-fidelity for subsequent twelve-month durations. This retains near-term work sharp with out losing effort on distant targets the place uncertainties might stay.

Determine 2: The second precept, time-phasing, places the best constancy within the near-term phases of the plan.
Uncover issues early: Mapping dependencies between every workforce’s waypoints identifies coordination gaps and bottlenecks earlier than they grow to be crises. Moreover, “orphan” waypoints at the moment are simply noticed. Whereas the exercise should be necessary to the group, if it isn’t crucial to realize the foremost programmatic aim, it needs to be thought-about for elimination from the sight image, with a purpose to keep a easy view of crucial actions to achieve the aim. Whereas the exercise should be necessary to the group, if it isn’t crucial to realize the foremost programmatic aim, it needs to be thought-about for elimination from the sight image. This helps keep a streamlined view of crucial actions essential to achieve the aim.

Determine 3: The third precept, uncover issues early, maps dependencies between waypoints to establish gaps and bottlenecks.
We realized that for organizations to efficiently undertake Waypoints, they would want three crucial management and workforce commitments:
- management endorsement with out mandate (creating “pull” somewhat than “push”),
- a lean motivated launch workforce, and
- a assure {that a} workforce’s updates to their waypoints will take not more than 5 minutes.
With these commitments in place, as proven under with our early-adopter groups, Waypoints replaces the dreaded quarterly PowerPoint replace.
Piloting Waypoints and the 5-Minute Assure
To pilot the Waypoints Framework, we recognized three early-adopter groups that had been fluent in digital instruments like Jira and Confluence. After sitting down with these three groups and figuring out their waypoints in addition to upstream and downstream dependencies, inside 1 / 4, we had been capable of efficiently launch their packages into this framework and reveal the advantage of visualizing their actions in light-weight digital instruments.
The workforce leaders who piloted Waypoints shortly realized that it allowed them to be prepared for any programmatic overview inside 5 minutes, a big worth proposition as they beforehand had spent one-to-two days getting ready PowerPoint slides every quarter.
Waypoints additionally considerably improved workforce communication. We offered Waypoints as a collaboration device—not a piece tracker—an important distinction that decreased adoption resistance. Leaders within the early adopter organizations inspired however didn’t mandate adoption, and groups proved receptive to new approaches.
Waypoints identification workshops helped groups visualize plans and perceive scope. We carried out dependency mapping workshops that uncovered incomplete handoffs early, enabling plan corrections earlier than issues materialized.
The groups that piloted Waypoints additionally turned disciplined about scoping, capturing solely the work important to programmatic objectives.
Scaling Challenges and Options
Adoption inside the group was so profitable that the Launch Group turned a constraint in serving to groups construct their waypoints and dependencies between groups that have to be visualized and managed to make sure handoffs are profitable. In piloting our framework, we realized that we would have liked to establish at the least one change agent on every workforce and empower them to study the digital tooling to assist scale the trouble. As an alternative of groups ready on the Launch Group’s calendar availability, we might have unfold the trouble extra evenly throughout the group.
We additionally got here to know that we would have liked to have a plan to transition to execution of the work. A transparent level of contact inside the group have to be recognized because the particular person accountable and empowered for orchestrating all groups’ actions with a purpose to attain the foremost programmatic aim.
Even in a company that has a excessive belief tradition, we discovered that configuration management of the Jira information turned essential. Our enterprise intelligence depends on the accuracy of the information, so we discovered that assigning a knowledge steward (i.e., a person who actually understands the community of waypoints that may result in profitable completion of the aim) to be essential.
Future implementations of the Waypoints Framework will incorporate the designation of workforce members to every of those key roles, constructing upon the always-evolving, always-improving blueprints we study when packages embark on the Waypoints Framework journey.
Curious about Adopting Waypoints?
Working in acquisition requires a endless cycle of reporting that leaves little time to deal with fixing issues or reaching objectives. The Waypoints Framework is designed to streamline that course of and permit program managers to deal with their mission objectives, usually with their present program administration instruments.
Efficient program administration shouldn’t require large forms. Impressed by a routine navigational idea from aviation, we now have created a framework that enables protection packages to realize formidable targets by incremental coordinated packages. In piloting the Waypoints Framework, we realized that each organizational setting is a singular journey that may require changes. One advantage of working on the SEI is that by our work with main protection packages, we now have encountered and gained an appreciation for various buyer environments and understanding the distinctive tailoring that can be required for every situation.
If you’re enthusiastic about working with the SEI to undertake the Waypoints Framework, please ship an e-mail to [email protected].